Sheffield Rotherham Parkway now fully open to traffic after extra lanes installed

Watch more of our videos on Shots! 
and live on Freeview channel 276
Visit Shots! now
Works to add a new lane to the Sheffield-Rotherham Parkway and introduce a new speed limit are now complete.

The £46m project began in February 2021, and includes an extra lane eastbound and westbound; resurfacing at J33 of the M1; speed limit reduction from 70mph to 50mph and new lighting and signs.

Read More
£46million works to widen Sheffield Parkway set to get underway

Rotherham council say the scheme has “markedly increased” capacity, improving journey times, and the new speed limit “will improve road safety and cut carbon emissions”.

Hide Ad
Hide Ad
The £46m project began in February 2021, and includes an extra lane eastbound and westbound; resurfacing at J33 of the M1; speed limit reduction from 70mph to 50mph and new lighting and signs.The £46m project began in February 2021, and includes an extra lane eastbound and westbound; resurfacing at J33 of the M1; speed limit reduction from 70mph to 50mph and new lighting and signs.
The £46m project began in February 2021, and includes an extra lane eastbound and westbound; resurfacing at J33 of the M1; speed limit reduction from 70mph to 50mph and new lighting and signs.

New street lighting, carriageway surfaces, signals and signs have been installed to improve safety, as well as drainage improvements to to create better flood resilience.

Councillor Denise Lelliott Rotherham Council’s cabinet member for jobs and the local economy, said: “The road is vital in connecting Rotherham with Sheffield and links to the M1. Completion of these works will make a big difference to thousands of commuters’ journeys every day as well as supporting economic and housing growth in the region.”

The improvements, which were funded through Central Government from the Local Growth Fund, have been carried out in partnership with leading international infrastructure group Balfour Beatty..

Stephen Semple, Area Director at Balfour Beatty, said: “Testament to the dedication and hard work of our team over the last 18 months, we are pleased that the A630 Rotherham Gateway scheme has now fully reopened to traffic.

“We hope that these essential upgrade works will provide a lasting legacy for South Yorkshire and beyond, improving lives through increased connectivity and reduced journey times.”